Irrigation
Interests Threaten Precious Hoopa Tribal Fisheries
Since time
immemorial, the Trinity River
of Northwest California has been
the life blood of Hoopa
Indian culture and subsistence. The
Trinity is the largest tributary of the mighty Klamath River
and it joins
the Klamath about 45 miles from the Pacific Ocean. Preserving the fish and other aquatic life of
those rivers is a constant struggle for the Hoopa Valley Indian Tribe. This
page provides a summary and links to documents describing the tribe’s struggle
to protect these resources.
1.
The Battle to Restore
the Trinity. In 1963, the Trinity
River was dammed by the U.S. Interior Department and “surplus”
water began to be pumped over to the Sacramento River
from Lewiston, California,
near Weaverville, in Trinity County. The 1955 law that authorized the dam
prohibited excess water diversions because of the injuries that could cause to
fish and people downstream along the Trinity River. Even in 1955, Congress knew that fish do
poorly without water.
After 37 years of neglect of the
Secretary’s duty to take “appropriate measures to ensure the preservation and
propagation of fish and wildlife,” 69 Stat. 719, Congress grew impatient with
the slow pace of fish protection efforts and in 1992 enacted Section
3406 (b)(23) of the Central Valley Project Improvement Act, Pub. L.
102-575. This new law was passed “to
meet Federal trust responsibilities to protect the fishery resources of the Hoopa
Valley Tribe.” In it, Congress ordered
completion of the ongoing Fishery
Flow Evaluation Study (large file) and implementation of its conclusions;
it also set a minimum amount of 340,000 acre-feet to be allowed to flow down
the Trinity River.
This amount is equivalent to the third-lowest unregulated flow in the
river.
On December 19, 2000, Interior
Secretary Bruce Babbitt traveled to Hoopa California, where he and the
Tribal Chairman signed a Record
of Decision setting forth the plan for Trinity River
restoration. The heart
of that plan is increasing the water left in (released to) the Trinity
River. The ROD also
provided for a detailed Implementation
Plan. The amount of water released
to the River depends on the “water year type” (wet, dry, normal, etc.). The ROD also allows more than half of the
Trinity’s flow at Lewiston to
continue to be exported through tunnels into the Sacramento
Valley.
Even before the Record of Decision (“ROD”) was
signed, Westlands Water District, a huge San Joaquin
Valley irrigation entity, sued to
block Trinity River restoration. While the Westlands case delayed restoration
for some time, the courts eventually sided with the Hoopa Valley Tribe, allowed
increased water releases to the river and directed the Interior Department to
carry out other restoration work.
In the
first four years after the ROD was signed in 2000, water releases to the Trinity
River were set by the federal courts. In
2001, District Court Judge Oliver Wanger ruled that the Interior Department
must prepare a new Environmental Impact Statement on the restoration work
effect, but he permitted the critically dry water amount, 369,000 acre-feet, to
be released, which was appropriate under the ROD for that very dry year. In early 2002, the Hoopa Valley Tribe filed a
motion to modify
the preliminary injunction and the Court authorized release of 468,600
acre-feet of water to the Trinity River.
On December
10, 2002, Judge Wanger issued a Memorandum Decision and Order ruling that
the Interior Department violated two environmental laws when it issued the 2000
ROD and directing that a revised Environmental Impact Statement be
prepared. The Tribe appealed. In
2003, the Court authorized the Department to release 453,000 acre-feet of
water for the Trinity River, plus use an additional
50,000 acre-feet if necessary for late summer conditions. In
2004, the Ninth Circuit Court of Appeals granted the Hoopa Valley Tribe’s
request to use 647,000 af (the normal year volume) for water
releases to the Trinity River.
In June
2004, Interior requested additional time to complete the Supplemental
Environmental Impact Statement for Trinity River
restoration. The Court granted
that request and extended the time for completion of the SEIS. The District Court’s docket
sheets show the details of the continuing litigation. The SEIS is available
for review at http://www.usbr.gov/mp/mp150/envdocs/trinity_seis/index.html
On July 13, 2004, the Ninth
Circuit Court of Appeals reversed all but one of Judge Wanger’s
rulings. The court held that no SEIS is
needed. The purpose and need statement and the range of alternatives examined
in the 2000 FEIS were adequate. The use of power plant bypasses for temperature
control was fully examined. The ROD’s effect on California’s
energy reliability was insignificant and did not require supplementation. The court upheld the ruling that Fish and
Wildlife’s Biological Opinion RPM which
limited movement of the X2 point in the Bay Delta and NMFS’ RPM
which required immediate implementation of ROD flows were invalid because they
required major changes in the proposed restoration action. Those RPM
are unenforceable but the Biological Opinions are otherwise valid.
Westlands and NCPA petitioned for
panel rehearing and rehearing en banc but, on November 5, 2004, the Ninth Circuit Court of
Appeals rejected
both petitions. The court noted that no judge requested a vote on the
petitions for en banc review. No party
petitioned for Supreme Court review so the Ninth Circuit ruling is the law of
the land.
While the Ninth Circuit ruled that
“nothing remains to prevent the full implementation of the ROD, including its
complete flow plan for the Trinity River,” the ROD’s
success depends on restoration work in the Trinity watershed as well as flows. The ROD permits the
Bureau of Reclamation’s Trinity River Division to
export of over 50% of the Trinity flow at Lewiston,
CA to the Central
Valley, so successful restoration
using the remaining water requires intensive habitat restoration work.
Within the first three years after the ROD, the Trinity Management Council was
to complete bank restoration work at 24 sites below Lewiston Dam. They actually completed zero. In 2004, the TMC appointed a subcommittee to
examine its lack of progress and got a scathing
report. Instead of rectifying the faults, Reclamation proposed to cut the fiscal
year 2005 funds for restoration.
In 2005-08, the pattern of
under-funding restoration work has continued. The Hoopa Valley Tribe and others
have been assisted by Sen. Dianne Feinstein and Congressman Mike Thompson in
adding funds to the inadequate amounts requested by the Bush Administration. In
2007, Congressman Thompson introduced H.R. 2733, a bill to assure that the
funding promised in the ROD would be provided. The Bureau of Reclamation and
its Central Valley agribusiness allies opposed the bill,
and it failed. Lacking adequate funds,
and hampered by Reclamation interference, the TMC has failed to restore key
river sites, such as Vitzhum
Gulch, to meet their potential. Thus, continuing problems of inadequate
funding and poor restoration performance are of great concern to the Hoopa
Valley Tribe and are the subject of continuing negotiations and discussions.
2.
2002--Largest Recorded Die-Off of Adult Salmon in the Klamath. Meanwhile, the Klamath River
portion of the Trinity River fish migration path has
become increasingly hazardous. In 1993, the Interior Department
Solicitor ruled that when the United States
set aside what are now the Hoopa Valley
and Yurok Indian Reservations, it reserved for the Indians a federally
protected right to sufficient fish to support a moderate standard of
living. Implementation of that ruling
was unsuccessfully challenged in Parravano
v. Babbitt. The court
upheld the Indian fishing right and the Supreme Court denied review in
1996.
The Klamath River,
one of the largest rivers of the West Coast, has historically been a huge
producer of salmon for ocean, tribal and recreational fishermen. Until recent years, salmon and steelhead
returns to the main stem Klamath and its tributaries above the Trinity exceeded
those returning to the Trinity itself. No more. The Bureau of Reclamation’s
construction of the Klamath Irrigation Project near Klamath Falls, Oregon, and
the subsequent construction of fish-blocking dams on the Klamath between there
and Interstate 5 in California, spelled the demise of most main stem fish
resources. Nevertheless, in 1995 and
again in 1997,
the Interior Department Solicitors ruled that the Bureau of Reclamation’s
Klamath Irrigation Project (upstream of the Indian reservations) must ensure
that its operations not interfere with the tribes’ rights to water for fishery
purposes. However, the Bureau of Reclamation has not followed that direction.
In 2002, between 34,000 and
68,000 adult
Chinook salmon died
in the Lower Klamath River below the confluence with the
Trinity. Analysis showed that most of those fish would have returned to the Trinity
River but for the reduced flow of bacteria-laden water they met
downstream. As a result, the Hoopa
Valley Tribe intervened
as a plaintiff in a suit by the Pacific Coast Federation of Fishermen’s
Association against the federal agencies controlling Klamath River
water releases. On July 14,
2003, Judge
Armstrong ruled that the agencies had violated the Endangered Species Act
by denying water to fish and assuming that others would provide enough water
for Coho salmon to survive. (The agencies
permitted water to be withdrawn from the Upper Klamath for irrigation
purposes.)
On October 18, 2005, the Ninth Circuit Court of
Appeals affirmed
the PCFFA ruling, noting that the agencies disregarded the life cycle of the
species. The Court said, “all the water in the world in 2010 and 2011 will not
protect the coho, for there will be none [then] to protect.” On remand, Judge Armstrong issued an injunction
directing the Bureau of Reclamation to limit irrigation water diversions if
they would cause the river to fall below 100% of the long-term
flows required by the Biological Opinion to protect salmon.
In 2003, Judge Armstrong also
ruled that a trial would be necessary to determine if the federal agencies
violated trust obligations owed to the Hoopa
Valley and Yurok Tribes by killing
the returning fish. Michael Kelly, the
lead biologist for National Marine Fisheries Service, had resigned in
protest because of Reclamation’s interference with the 2002 Biological
Opinion preparation, interference which led to the low water flows permitted
that year by the BiOp (flows that the Judge later enjoined.) Nevertheless, scientific analysis
of the 2002 fish die-off pointed to several causes besides the unnaturally
low water flows, so the extent of culpability of the Bureau of Reclamation was
unclear. As a result, the Hoopa Valley
Tribe and the federal defendants entered into a settlement in October 2004
under which a technical consultation group will be created and crucial
fisheries studies will be funded for a few years. The Yurok Tribe did not settle its claim but
it was dismissed
before trial on jurisdictional grounds. The Tribe’s appeal of that dismissal
was settled
in 2006.
3.
Remove Klamath Dams to Restore Fish! In 2006, the 50-year federal license to
operate six dams blocking the Klamath River expired. The
Hoopa Valley,
Klamath, Karuk and Yurok Tribes have all intervened in proceedings before the
Federal Energy Regulatory Commission (FERC), P-2082, regarding whether and how
that license should be reissued to the electric utility, PacifiCorp.
Several of the fish-blocking dams
of the Klamath were built before the Federal Power Act was passed in 1920.
While they generate little electricity, they also have few operating costs so
they are popular with the utility.
However, many new laws protecting the environment and tribal fisheries
have been passed since the Klamath Project license issued in 1956 and no new
license can be issued to the Project without satisfying current laws.
In March, 2006, the Interior
Department and National Marine Fisheries Service issued federal land protection
conditions and fish passage “prescriptions” as authorized by sections 4(e) and
18 of the Federal Power Act for the dams. (The three dams in the California
portion of the Klamath River have no fish ladders or
screens whatsoever!) These called for full volitional upstream and
downstream fish passage. There are, of course, currently no salmon runs above
Iron Gate Dam, the lowest structure in the Klamath Hydroelectric Project, since
no fish passage was constructed when Iron
Gate was built in 1961. See
Cal. Ore. Power Co. 25 F.P.C. 579 (Mar. 27, 1961). PacifiCorp responded by invoking a new
federal law, the Energy Policy Act of 2005, and demanding a hearing on disputed
parts of those conditions and prescriptions, challenging the federal agencies’
authority. Orders, briefs and transcripts of that hearing are outlined and
linked here.
At the conclusion of a week of trial, in 2007 Judge McKenna upheld
substantially all of the fish and water protection measures.
In
November 2006, the California Energy Commission in cooperation with the
Department of the Interior released a report on Klamath dam decommissioning
costs, Economic Modeling of Relicensing and Decommissioning Options for the
Klamath Basin Hydroelectric Project. PacifiCorp responded to the Report by retaining
Christensen Associates Energy Consulting, LLC (“CAEC”) to review the Report.
CAEC contended that it found several flaws and argued that, with their
corrections to the CEC Report, relicensing the Klamath Hydro Project would
cost $46 million less than decommissioning. The CEC
replied by issuing an
addendum to its original report. The CEC
insists that relicensing, including mitigation costs, creates the highest risk
for PacifiCorp rate payers. Id. The CEC Report has been subsequently reinforced by the
Federal Energy Regulatory Commission Environmental Impact Study conclusions.
The
FERC relicensing proceeding reached a plateau in November 2007 with issuance of
the Final Environmental Impact Statement for Hydropower License,
FERC/FEIS-0201F. The FEIS examined PacifiCorp’s application with the Commission
for a new license for the Klamath Hydroelectric Project, which is located
principally on the Klamath
River in Klamath County, Oregon and Siskiyou County, California, between Klamath Falls, Oregon and Yreka,
California. The Klamath Project has a capacity rating of 169
megawatts (MW), about 2% of PacifiCorp’s total capacity, and it generates about
1% (716,800 MWh) of PacifiCorp’s average electricity production. The current
license expired on March 1, 2006, and the Project is operating under a third annual
license.
The Executive
Summary of the FEIS shows the possibility of retiring the Copco No. 1 and
Iron Gate Dams, as well as retirement of J.C. Boyle, Copco I, Copco II and Iron Gate
developments. Table ES-1, summarizes the effects of various alternatives,
showing that complying with the mandatory fishway conditions produces a net
annual loss of $20.2 million, retirement of Copco I and Iron Gate Dams would
produce a net annual loss of $6.6 million benefit; and retirement of all of the
dams, a net annual loss of $13.2 million.
4. Hijacking Dam Removal Negotiations and the
KBRA. The
deeply negative economic “benefits” of relicensing the Hydroelectric Project
while complying with the Clean Water Act, the Endangered Species Act, and
Indian fishing rights, created an opportunity for the parties to negotiate
concerning retirement and removal of some or all of the dams. Unfortunately,
under the pro-agribusiness Bush Administration, this fit nicely into the Bureau
of Reclamation’s and irrigation interests’ (led by the Klamath Water Users
Association) plan to establish priority for their water rights over those of
the Indian Tribes in Oregon and downstream in California. (The tribes currently
have senior, and thus priority, water rights.) What has followed is a long series
of negotiation sessions, at first presided over by the Interior Department’s
representatives, but later by a mediator hired by the Department.
On
January 15, 2008, approximately 20 negotiating parties (not including the
dam licensee, PacifiCorp) released Draft 11 of the Proposed Klamath River Basin
Restoration Agreement for the Sustainability of Public and Trust Resources and
Affected Communities (“KBRA”).
That partial agreement proved both incomplete and highly controversial. It was
incomplete because it depended for its effectiveness upon completion of a
Klamath Hydroelectric Project Settlement Agreement, a document which did not
then exist (see below).
The
proposed KBRA was controversial because it guaranteed water to
irrigation and refuge users but did not guarantee water for Upper
Klamath Lake or instream flow of the Klamath River
downstream of the irrigation project. Analysis of the water flows projected below the
irrigation diversions showed that despite enlargement of Upper Klamath Lake and
some planned water efficiencies in the Upper Basin, in approximately
40% of water year types, the river levels would not satisfy the flows
required by the National Marine Fisheries Service’s Biological Opinion regarding
the Bureau of Reclamation’s Klamath Project operations from June 1,
2002, through March
31, 2012. Table 9 of that
document (BiOp
at 70) prescribes
the recommended long-term Iron Gate Dam discharge levels by water year type, a
set of requirements made mandatory by Pacific Coast Federation of
Fishermen’s Ass’n v. U.S. Bureau of Reclamation, U.S.D.C. N. Cal. No.
C-02-2006 SBA, Order
Granting Motion for Injunctive Relief following Remand (Mar. 27, 2006). Thus, the
proposed KBRA will frequently fail to meet the needs of fish.
The proposed KBRA also calls for
federal appropriations of $985 million
and confers many benefits on Klamath Project irrigators including $41 million
in power subsidies; $92.5 million to implement their own water plan that they
develop without public oversight; preferential Columbia River hydro-system
power rates; debt forgiveness on disputed Klamath Project capital costs owed to
the United States; special contracts on project operation, maintenance and
pumping costs that need legislative exemptions from the cost sharing provision
of the Reclamation Reform Act of 1982; support for continuing commercial
leaseland farming on national wildlife refuges for 50 years; 80% of the revenue
paid for farming refuge lands goes back to their benefit by payments of 10% of
the revenue to Tulelake Irrigation District, 10% of the revenue to Klamath
Drainage District, and approximately 60% to the Bureau of Reclamation to reduce capital costs of the Klamath
Project that would otherwise be recoverable from the Project irrigators; U.S. Fish & Wildlife Service picking up a
greater percentage of the pumping costs for operating the D plant that drains
Tule Lake for farming; Reclamation assuming all costs for operating Link River
Dam and Keno Dam for Project diversion, a substantial portion of which costs
should be paid by Project irrigators under current cost-sharing laws; and
finally regulatory assurance benefits, intended to shield activities from the
Endangered Species Act.
On November
13, 2008, Interior Secretary
Dirk Kempthorne announced an Agreement in Principle with PacifiCorp. The Agreement
in Principle (“AIP”) defines “a path forward” from which there are many
exits for the utility. Each exit (right to withdraw from the Agreement) ends
the non-binding plan for removing four dams and restarts the FERC licensing
process. Under the AIP, no decision whether to remove a dam can be made
before March 31, 2012, at the earliest. Thus the main effect of the AIP
now is to halt and delay the water quality certification analysis (required by
the Clean Water Act) which was underway in California and Oregon, and suspend the FERC relicensing process.
The AIP
envisions negotiation toward a Final Agreement in late 2009. The affected
Indian tribes are not parties to the AIP
and were permitted to observe
the subsequent negotiations only if they accepted the AIP as the basis of negotiations and refraied
from seeking “to reopen resolved” issues. Enactment of federal legislation is a
condition of the “path forward;” it must ratify a separate agreement, the
Klamath Basin Restoration Agreement (“KBRA”), authorize the United States to
conduct studies, and direct the United States to make a determination, by March
31, 2012, of whether the
benefits of dam removal justify the potential costs, risks, liabilities, etc. §
3, p. 6. The states of Oregon
and California may exercise a right of withdrawal within sixty days
if they disagree with the United States’ 2012 determination.
In
the interim between now and approximately 2021, the licensing process and water
quality evaluations are stalled and the Project continues generating power
without necessary conditions to protect fish health, habitat, or water quality.
The AIP also requires Oregon and California each to secure by legislation a total state
contribution toward dam removal of $200 million from power customer rate
increases. In addition, the State of California must obtain voter approval of a general obligation
bond for an additional $250 million for dam removal. Failure of any of these
pieces of legislation will end the Agreement.
The
federal legislation required by the AIP
will direct the United
States
to designate a dam removal entity, which must be a non-federal entity qualified
to remove the dams, defend any litigation, pay all damages, and provide
complete protection from liability for PacifiCorp. § 4, p. 7, § VIII, p. 15.
Having a non-federal entity perform these functions, if a qualified entity can
be found, will lead to higher insurance and defense costs than if the federal
government took the responsibility.
Under the AIP,
PacifiCorp will operate the dams pursuant to the annual extensions of its 1956
license until decommissioning of each individual dam, which would begin, at the earliest, in 2020. Interim
conditions on operations may be included in the Final Agreement to be
negotiated. Also, PacifiCorp, the National Marine Fisheries Service and U.S.
Fish and Wildlife Service have approved an Interim
Conservation Plan (a subset of the minimal interim measures mentioned in
the AIP) which will be added to PacifiCorp’s annual license.
The Interim Conservation Plan utterly fails to meaningfully address the
significant threats to fish health and water quality that plague the river.
On September
30, 2009, PacifiCorp and
other parties reached a tentative Klamath Hydroelectric
Settlement Agreement, (“KHSA”) prepared along the lines of the Agreement in
Principle. As with the AIP,
performance of this agreement requires separate federal and state legislation
to be passed, and it ensures that PacifiCorp may continue to operate the
ancient hydroelectric project for many years to come. The KHSA blocks the FERC relicensing
proceeding and instead prescribes a planning process which might, but might not, result in removal of some or all of the dams that block
Klamath River fish. A slightly modified version of the
KHSA was released for public review on January 8,
2010.
Also
on January 8, 2010, the parties
released a new version of the KBRA, discussed above. The KBRA, although
revised from the January 15, 2008 version, continues to have the following
short-comings: (1) No guaranteed river flows for fish; (2) Requires non-federal
parties' support of continued leaseland farming on NWRs for at least 50 more years, creating a political
gridlock for progress; (3) Provides more water for irrigators than is currently
allowed under the existing BiOp/ESA; (4) Requires
non-federal parties to support changing the Biological Opinion protecting coho salmon to enable the irrigators to divert desired
water; (5) Provides nearly $50 million in subsidies for irrigators; (6) Does
not have a ready drought or climate change plan; (7) Limits the water rights of
all Klamath basin tribes without all tribes' consent.
On
February
18, 2010, slightly revised
versions of both the KBRA
and the KHSA were signed by many parties. Federal agencies did
not sign the KBRA because of the need for new legislative authority.
The road is
long, but the continuing efforts of the Hoopa Valley Tribe and its local and
environmentally conscious allies will lead slowly, but ineluctably, to the
restoration of one of California’s most beautiful and precious rivers, the
Trinity, and the Klamath River basin.
T:\WPDOCS\0020\05543\Corresp\CV Interest071204_01.doc
nmc:9/20/06